
Energy Efficiency client case study – Clínica Farallones
Clínica Farallones is a healthcare facility in the city of Cali, Colombia.

Project context
Clínica Farallones, with levels three and four of complexity, is located in the city of Cali and boasts modern architecture that has been enhanced by natural light.
The client was looking to implement an Energy Efficiency project to cut costs on his bills, while maintaining the comfort he already enjoyed. Specifically, he requested the supply of cold water for the clinic’s air conditioning, in addition to the installation of equipment for a specific area, sterilization, accompanied by regular maintenance of the equipment that GreenYellow installed for this purpose.
Do you have similar challenges?
Project highlights
-
Meeting the constant demand for energy in the hospital sector
-
Preventive, predictive and corrective maintenance to ensure that equipment is in good condition
-
View alarms in real time
-
Connecting heat pumps to the system
-
Installation of a 160-ton chiller in the chilled water system to supply cold water for air conditioning.
-
Installation of heat pumps and use of heated water when extracting heat from the heated zone to generate hot water for showers and improve chiller efficiency
-
Dual use of hot and cold energy
-
Thanks to the savings on the electricity bill, the clinic can invest in machinery, technology or the hiring of specialists.
- Type of contract: EPC | Cooling and heating system
- Number of sites: 1
- Start of contract: 05/2020
- Length of contract: 8 years
Project key figures
37,3%
energy saving
0.7 GWh
annual savings
98 tons
CO2 emissions avoided
0%
client investment
Share this article
Other Energy Efficiency client case studies
Ensemble, construisons votre
projet d’efficacité énergétique