Energy storage client case study – Stellantis España
Stellantis is a multinational conglomerate dedicated to manufacturing automobiles and providing mobility services.
Project context
The Stellantis plant in Madrid is a key production center for the company in Europe. Formerly known as the PSA plant in Villaverde, it is located in the Villaverde district, south of Madrid, Spain. As part of their decarbonization plans, they have entrusted GreenYellow with three key pioneering initiatives: a photovoltaic power plant, a storage battery, and heat pumps.
Do you have similar challenges?
Project highlights
- Carry out three projects simultaneously, constantly adapting to the client’s circumstances
- Optimize production by making the best use of available space
-
100% self-consumption, as surpluses are stored in the battery and can be used when the client needs them
-
When it was developed, it was the largest self-consumption battery in Europe.
-
A pioneering tripartite project at GreenYellow, working together to meet the client’s zero-emissions target
-
Commitment to energy transition and CO2 reduction
- Type of contract: BESS + PPA + EPC
- Number of sites: 1
- Start of contract: 12/2024
- Contract length:15 years
Project key figures
25 MWh
total storage capacity
18.8 MWh
total solar production capacity
0%
client investment