Energy Efficiency client case study – Valéo

Valeo is a French group and one of the world’s leading automotive suppliers.

Project context

Valeo has reaffirmed its confidence in GreenYellow, following the success of several projects (Angers, Etaples), by entrusting it with the installation of a new cold unit with heat recovery at its Mazamet site, via an 8-year energy performance contract.

Do you have similar challenges? 

Project highlights

  • Turnkey project Supervision: equipment communication, setting up a measurement and verification plan, monitoring energy performance indicators, sending alerts.

  • Reducing energy consumption

  • Modernization with high-performance chillers with heat recovery and storage
  • Air treatment: installation of 7 AHUs and destratifiers to replace unit heaters
  • Installation of a 1,000 kVa transformer
  • Reducing energy consumption and costs at the Valeo site
  • Guaranteed energy performance of 1.49 GWh/year
  • Improved thermal comfort in workshops and offices
  • Type of contract: EPC | INDUSTRIAL COOLING
  • Number of sites: 1
  • Start of contract: September 2022
  • Length of contract: 8 years

Project key figures

63 %

energy savings

70 tons

CO2 emissions avoided

0%

client investment