Energy Efficiency Client Case Study – Stellantis España

Stellantis is a multinational conglomerate that manufactures automobiles and provides mobility-related services

Project context

The Stellantis plant in Madrid is a key production facility for the company in Europe. Formerly known as the PSA plant in Villaverde, it is located in the Villaverde district, south of Madrid, Spain. As part of their decarbonization efforts, they entrusted us with three key, pioneering initiatives: a solar power plant, a storage battery, and heat pumps.

Do you have similar challenges? 

Project highlights

  • Significantly reduce CO2 emissions from natural gas boilers

  • Ensure the comfort and well-being of employees at the factory

  • Replacing natural gas boilers with heat pumps

  • Ensure effective air conditioning in the factory’s workspaces

  • A pioneering three-part project by GreenYellow that aligns with the client’s goals for reducing emissions

  • Demonstrates a strong commitment to the energy transition and a substantial reduction in CO2 emissions

  • Supporting the transition to sustainable energy practices

  • Contract Type : EEA | Heat pump
  • Number of sites: 1
  • Start of contract : 12/2024
  • Contract length:15 years

Project key figures

2.9 GWh

Energy savings

57%

savings compared to the previous system

1,218 tons

CO2 emissions avoided