Client Case solar photovoltaic - BITCO

BITCO is one of the main transport and logistics terminals in the regional port of Barranquilla, Colombia.

Project background

In order to reduce its carbon footprint and promote greener management of transport/logistics activities, the Port of Baranquilla was looking to use a greener source of energy.
As part of its #SHIFTProduction offer, GreenYellow designed and developed a bespoke project: a rooftop photovoltaic solar plant .

As a result, the BITCO terminal will benefit from green, local and competitively-priced electricity to cover part of its energy needs.
It will also enable the port to reduce its carbon footprint, while reinforcing its position as an eco-responsible player on a regional scale.

Do you have similar challenges? 

Key points of the project

  • Accelerate the port of Barranquilla's energy transition by implementing a tailor-made project for its BITCO terminal.
  • Using clean energy
  • Reinforce the position of this regional port as aneco-responsible player, with the aim of becoming the main logistics hub in the Colombian Caribbean.
  • Decentralized green electricity generation
  • Self-consumption of green, local and competitively priced electricity
  • Project under construction
  • Lower energy costs
  • Predictable costs
  • Reducing carbon footprint
  • Long-term guaranteed energy
  • Contracttype : PPA | Rooftop power plant
  • Number of sites: 1 main terminal dedicated to transport/logistics
  • Contractstart date: 09/2023 
  • Contractduration : 10 years

Key figures

2 MWp

of installed capacity

3 GWh

Annual production

0%

investment client

Other Client Cases in solar photovoltaics

Let's analyze together
the ecological and financial impact
of your energy optimization.

Our experts will contact you to understand your needs and develop your turnkey project, 100% financed!

Follow us

2023 GreenYellow, all rights reserved